SuperFloor Installation

superfloor_drawing

Fixing Detail In Suspended Floor Applications

Superfloor Foil is rolled out with the foil facing upwards, over the joists

The pipework is then clipped through into the insulation layer using the specially designed YBS Pipe Clips to maintain required air gap – 5 per M²

The horizontal joints are overlapped by 50mm and are left open to allow for any moisture accumulation to dissipate

Superfloor Foil must then be brought up (behind the skirting board) to 75mm

The pipework is then laid starting from the manifold and then into the required room (see drawing). The pipe is then laid at uniform centres of approximately 200mm centres, notching where necessary.

The decking is then fixed with screws (at 200mm centres) into battens/joists providing 25mm penetration into the 50mm wide battens/joists

Fixing Detail In Solid Ground Floor Applications

SuperFloor Foil is rolled onto concrete floor with shiny side facing upwards – leaving enough edge overlap for 75mm lip to be left behind skirting

Timber battens/joists (min 50mm x 50mm) are then laid on top of the Superfloor Foil, spaced at centres to suit the particular flooring

Superfloor Clips are fixed to the battens/joists 5 per m2

The decking is then fixed with screws (at 200mm centres) into battens/joists providing 25mm penetration into the 50mm wide battens/joists.