Installation
- Foil-Tec Double is
rolled out over the joists
- Foil-Tec Double is
then nailed in place through the Foil-Tec Saddle Clips
to maintain required air gap - 4 per m²
- The horizontal joints are overlapped by 100mm and are
left open to allow any moisture accumulation to dissipate
- Foil-Tec Double must
be brought up (behind the skirting board) to 75mm
- The decking is then fixed with screws (at 200mm centres)
37mm into the joists
Joist End Fitting
Recommendations
Make 2 x 75-100mm cuts in Foil-tec - same width as joist. Then make one further
cut, same width again, on each side. Fold up flap(A), fold back flaps (B) and
pull Foil-tec (C) up to meet wall. Fix to
wall and fit skirting board over, concealing Foil-tec.
|