Fixing
Detail In Suspended Floor Applications
Superfloor Foil is rolled out with the foil facing upwards,
over the joists
The pipework is then clipped through into the insulation
layer using the specially designed YBS Pipe Clips
to maintain required air gap - 5 per M²
The horizontal joints are overlapped by 50mm and
are left open to allow for any moisture accumulation
to dissipate
Superfloor Foil must then be brought up (behind the
skirting board) to 75mm
The pipework is then laid starting from the manifold
and then into the required room (see drawing). The
pipe is then laid at uniform centres of approximately
200mm
centres, notching where necessary.
The decking is then fixed with screws (at 200mm centres)
into battens/joists providing 25mm penetration into
the 50mm wide battens/joists
Fixing
Detail In Solid Ground Floor Applications
SuperFloor Foil is rolled onto concrete floor with
shiny side facing upwards - leaving enough edge overlap
for 75mm lip to be left behind skirting
Timber battens/joists (min 50mm x 50mm) are then laid
on top of the Superfloor Foil, spaced at centres to
suit the particular flooring
Superfloor Clips are fixed to the battens/joists 5
per m2
The decking is then fixed with screws (at 200mm centres)
into battens/joists providing 25mm penetration into
the 50mm wide battens/joists.
|