Fixing Detail In Suspended
Floor Applications
- Superfloor Foil is rolled
out with the foil facing upwards, over the joists
- The pipework is then clipped through into the insulation layer
using the specially designed YBS Pipe
Clips to maintain required
air gap - 5 per M²
- The horizontal joints are overlapped by 50mm and are left open
to allow for any moisture accumulation to dissipate
- Superfloor Foil must then
be brought up (behind the skirting board) to 75mm
- The pipework is then laid starting from the manifold and then
into the required room (see drawing). The pipe is then laid at
uniform centres of approximately 200mm centres, notching where
necessary.
- The decking is then fixed with screws (at 200mm centres) into
battens/joists providing 25mm penetration into the 50mm wide
battens/joists
Fixing Detail In Solid
Ground Floor Applications
The screeded system comprises:
- The Superfloor edge strip - to be laid against all
external and internal walls, providing edge insulation
and an expansion zone for the screed.
- Superfloor insulation
board is laid on top of the concrete slab. (YBS provide a wide
range of thicknesses and types of
insulation to ensure the required insulating properties are
achieved.)
- Using the grid pattern - lay down the heating pipes
as planned, using
clips to fix position.
- Most situations will require 65-85mm thickness of
screed.
- Reinforcing mesh can be used where required.
- Expansion profiles are to be used where pipework
passes through an expansion joint.
|